Vision Iowa
While some of our Vision Iowa projects are still
underway, others have been completed and are being enjoyed by all.
Below is the lastest update on the status of all of the Vision Iowa
projects.
PROJECT COMPONENT STATUS
AQUATIC CENTER
Committee Chairperson - Brad Parker
Design Firm Selected - Water's Edge
Construction Firm Selected - Clinton Engineering
Budget/Funding
Total Project Component Budget -
$1,020,000
Design Firm Fee Amount - $75,250
Construction Contract Amount
-$872,068
Schedule
Design Compete -August 2005
Construction Initiated -November 2005
Construction Complete -May 2006
Current Issue/Events
Project construction is 99% complete
Pool was operational in summer 2006
Minor punch list items are being completed
BANDSHELL
Committee Chairperson - Wayne Larkey
Design Firm Selected - Gere/Dismer
Architects (Rock Island, IL)
Construction Firm Selected - TBD
Budget/Funding
Total Project Component Budget - $250,000
Construction Contract Budget - $231,481
Engineers Estimate of Construction - TBD
Design Firm Fee Amount - $18,519.00
Construction Contract Amount - TBD
Schedule
Design Complete - March 2006
Construction Initiated - July 2006
Construction Complete - Oct 2006
Current Issue/Events
Geotechnical issues have delayed the
project.
New plan and schedule are required
MARINA
Committee Chairperson - Dave Schnier
Design Firm Selected - JJR, LLC (Madison WI)
Construction Firm Selected - TriCon Construction
(North Phase)
Budget/Funding
Total Project Component Budget - $6,163,693
(Includes Abormarche Contract)
Construction Contract Budget -
$5,300,000
Engineers Estimate of Construction -
$5,300,000
Design Firm Fee Amount -
$468,380
Construction Contract Amount -
$900,000 (TriCon - North Phase)
$100,000 (Nutri-Ject - North
Dredging)
$384,000 (Wheatland - South Dredging)
Schedule
Design Compete - November 2005
Construction Initiated - June 2006
Construction Complete - 2008
Current Issue/Events
Project divided into North and South Phases
North Phase includes land work north of
flood gate
South Phase includes land work south of
flood gate and all docks
North dredging is complete
Amenities building contract is to be bid
December 07, 2006
South land work contract to be bid December
07, 2006
SHOWBOAT RENOVATION
Committee Chairperson - Tom Jankowski
Design Firm Selected - Gere/Dismer Architects
(Rock Island, IL)
Construction Firm Selected - Phase 1 - remaining
electrical work - Leslie Electric
Phase 2 - mechanical work - RHA Services
Exterior painting - Moehr Painting
Paddle Wheel Restoration - City staff
Budget/Funding
Total Project Component Budget -
$204,000
Design Firm Fee Amount -$15,111.00
Construction Contract Budget -
$188,889
Construction Contract Amount
Phase 1 $ 46,650
Phase 2 $ 35,225
Exterior Painting
$68,000
Paddle Wheel Restoration
-$10,000
Schedule
Construction Initiated - August 2005
Construction Complete - May 2006
Current Issue/Events
100% Complete
ALLIANT ENERGY FIELD
Committee Chairperson - Ted Tornow
Design Firm Selected - HOK (Kansas City, MO)
Construction Firms Selected - Portzen Const. and
Bush Seeding Co.
Budget/Funding
Total Project Component Budget -
$3,822,500.
Construction Contract Budget - $3,291,000
Construction Contract Amounts
Stadium - $2,850,000 (Portzen)
Field - $419,000 (Bush)
Total Construction - $3,269,000
Design Firm Fee Amount - $349,000.
Schedule
Design Complete - May 2005
Construction Initiated -July 2005
Construction Complete -March 2006
Current Issue/Events
Construction is complete
Closeout on-going
RV PARK AND AMMENITIES
Committee Chairperson - Mark Schroeder
Design Firm Selected - JJR, LLC (Madison, WI)
Construction Firm Selected - Langman Construction
Budget/Funding
Total Project Component Budget - $903,700
Construction Contract Budget - $740,000
Design Firm Fee Amount - $140,366.
Construction Contract Amount - $650,000
Tot Lot Equip + Tennis Ct Surface = $35,000
+ $11,500
Schedule
Design Compete -October 2005
Construction Initiated -December 2005
Construction Complete -July 01, 2006
Current Issue/Event
Construction 99% complete
Close on-going
SKATE PARK
Committee Chairperson - Gregg Obren
Design Firm Selected - Midwest Sales Company
(Davenport, IA)
Construction Firm Selected - Solo Ramps / Midwest
Sales
Budget/Funding
Total Project Component Budget - $114,835
Engineers Estimate of Construction -
$119,235
Design Firm Fee Amount -NA
Construction Contract Amount -$107,579 +
$4,156+ Lighting
Schedule
Design Compete - NA
Construction Initiated -NA
Construction Complete -August 2005
Current Issue/Event
100% Complete