What’s New
Vision Iowa

While some of our Vision Iowa projects are still underway, others have been completed and are being enjoyed by all. Below is the lastest update on the status of all of the Vision Iowa projects.


Alliant Field 28370_C264716.jpg








































PROJECT COMPONENT STATUS

AQUATIC CENTER
Committee Chairperson -  Brad Parker
Design Firm Selected - Water's Edge
Construction Firm Selected - Clinton Engineering
Budget/Funding
   Total Project Component Budget - $1,020,000
   Design Firm Fee Amount - $75,250
   Construction Contract Amount -$872,068
Schedule
  Design Compete -August 2005
  Construction Initiated -November 2005
  Construction Complete -May 2006
Current Issue/Events
  Project construction is 99% complete
  Pool was operational in summer 2006
  Minor punch list items are being completed

BANDSHELL
Bandshell 2.jpg
Committee Chairperson -  Wayne Larkey
Design Firm Selected -  Gere/Dismer Architects (Rock Island, IL)
Construction Firm Selected - TBD
Budget/Funding 
  Total Project Component Budget - $250,000
  Construction Contract Budget - $231,481
  Engineers Estimate of Construction - TBD
  Design Firm Fee Amount -  $18,519.00
  Construction Contract Amount -  TBD
Schedule
  Design Complete - March 2006
  Construction Initiated - July 2006
  Construction Complete - Oct 2006
Current Issue/Events
  Geotechnical issues have delayed the project.
  New plan and schedule are required

MARINA
Committee Chairperson - Dave Schnier
Design Firm Selected - JJR, LLC (Madison WI)
Construction Firm Selected - TriCon Construction (North Phase)
Budget/Funding
  Total Project Component Budget - $6,163,693 (Includes Abormarche Contract)
   Construction Contract Budget - $5,300,000
   Engineers Estimate of Construction - $5,300,000
   Design Firm Fee Amount -   $468,380
   Construction Contract Amount - $900,000 (TriCon - North Phase)
   $100,000 (Nutri-Ject - North Dredging)
   $384,000 (Wheatland - South Dredging)
Schedule
  Design Compete - November 2005
  Construction Initiated - June 2006
  Construction Complete - 2008
Current Issue/Events
  Project divided into North and South Phases
  North Phase includes land work north of flood gate
  South Phase includes land work south of flood gate and all docks
  North dredging is complete
  Amenities building contract is to be bid December 07, 2006
  South land work contract to be bid December 07, 2006

SHOWBOAT RENOVATION
Committee Chairperson - Tom Jankowski
Design Firm Selected - Gere/Dismer Architects (Rock Island, IL)
Construction Firm Selected - Phase 1 - remaining electrical work - Leslie Electric
Phase 2 - mechanical work - RHA Services
Exterior painting -  Moehr Painting
Paddle Wheel Restoration - City staff
Budget/Funding
   Total Project Component Budget - $204,000
   Design Firm Fee Amount -$15,111.00
   Construction Contract Budget - $188,889
   Construction Contract Amount  
     Phase 1  $ 46,650
     Phase 2  $ 35,225
     Exterior Painting  $68,000
     Paddle Wheel Restoration -$10,000
Schedule
  Construction Initiated - August 2005
  Construction Complete - May 2006
Current Issue/Events
  100% Complete

ALLIANT ENERGY FIELD
Committee Chairperson - Ted Tornow
Design Firm Selected - HOK (Kansas City, MO)
Construction Firms Selected - Portzen Const. and Bush Seeding Co.
Budget/Funding 
  Total Project Component Budget - $3,822,500.
  Construction Contract Budget - $3,291,000
  Construction Contract Amounts
  Stadium - $2,850,000 (Portzen)
  Field - $419,000 (Bush)
  Total Construction - $3,269,000
  Design Firm Fee Amount - $349,000.
Schedule
  Design Complete - May 2005
  Construction Initiated -July 2005
  Construction Complete -March 2006
Current Issue/Events
  Construction is complete
  Closeout on-going

RV PARK AND AMMENITIES
Committee Chairperson -  Mark Schroeder
Design Firm Selected - JJR, LLC (Madison, WI)
Construction Firm Selected - Langman Construction
Budget/Funding
  Total Project Component Budget - $903,700
  Construction Contract Budget - $740,000
  Design Firm Fee Amount - $140,366.
  Construction Contract Amount - $650,000
  Tot Lot Equip + Tennis Ct Surface = $35,000 + $11,500
Schedule
  Design Compete -October 2005
  Construction Initiated -December 2005
  Construction Complete -July 01, 2006
Current Issue/Event
  Construction 99% complete
  Close on-going

SKATE PARK
Committee Chairperson - Gregg Obren
Design Firm Selected - Midwest Sales Company (Davenport, IA)
Construction Firm Selected - Solo Ramps / Midwest Sales
Budget/Funding
  Total Project Component Budget - $114,835
  Engineers Estimate of Construction - $119,235
  Design Firm Fee Amount -NA
  Construction Contract Amount -$107,579 + $4,156+ Lighting
Schedule
  Design Compete - NA
  Construction Initiated -NA
  Construction Complete -August 2005
Current Issue/Event
  100% Complete


Back to Top
132_3216.jpg
Skate Park.jpg
ACCREDITATION_(web).jpg
131_3185.jpg
empty.png
empty.png
Iowa Great Places
Vision Iowa
What’s New
Bandshell.jpg
LumberKings crowd.jpg
pool lighthouse.jpg
IMG_659623364_Copy264712.jpg
Contact Us
View Map
Calendar
River City Gold
Our Community
Chamber of Commerce
Downtown Partnership
Community Partners/Links
Affiliated Organizations
Clinton Regional Development Corporation
Clinton County Community Development Association
Convention & Visitors Bureau/Tourism
Videos
Cultural & Entertainment District
Lyons District
Governmental Affairs
empty.png
2006 Clinton Area Chamber of Commerce    l   All Rights Reserved
721 South 2nd Street    l    Clinton, Iowa 52730    l    563-242-5702    l    chamber@clintonia.com